LOFAR Critical Design Review in Progress
The Critical Design Review for LOFAR
is under way. It is planned as a two phase process. First, roughly
every two weeks starting in mid-September, a series of six critical
reviews of the main sub-systems is being carried out:
(1) Antennas, receivers, ADC;
(2) Station digital processing;
(3) Monitoring, control, specification and scheduling;
(4) Wide area network and central processor;
(5) Calibration; and
(6) User software and key projects. Uncertainties resulting from
these sub-system reviews are expected to be resolved by early in
the New Year, when a final, full system level CDR will be held.
Following the latter, a definitive construction budget can be finalized,
and procurement and roll-out can begin. Land acquisition and planning
permission for the central core and inner stations are proceeding
well and are not expected to delay roll-out.
<
In case of questions
or comments regarding LOFAR, or about these web pages, please contact
lofar@astron.nl
Read this disclaimer
before proceeding.
Jobs
| Pictures
| Archives|
Sponsors
|